Solano STRIVE Playground Expansion
Fun new panels join the outdoor activity center for Solano's STRIVE students!
Encanto Playground Expansion
Check out what's happening with this MASSIVE expansion to the play areas at Encanto!
Montecito Montessori Spaces Re-Imagined!
We are completely renovating Montecito Community School to meet the needs of our ever-expanding Montessori program!
OMS Flexible-Use Auditorium Facility
What's happening with this impressive new facility that will be joining the Camelback Road cityscape?

-
2024-2026
Approx. $30 MillionClarendon Elementary School
- New Playground - COMPLETED
- Relocate Volleyball Court to Center Basketball Court
- Roofing
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Encanto Elementary School
- Add Play Structures and Expand Playground
- Roofing
- Weatherization
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Longview Elementary School
- Replace Existing Domestic HW Loop
- Replace Boiler
- Replace Existing Elevator
- Audio/Video for Stage, Lobby, and Gym
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Montecito Community School
- Interior Classroom Reconfigurations and Improvements to Meet District Standards
- Replace Elevator
- Replace Roof
- Parking Lot Renovation
- Screening Along 7th Street
- Develop Outdoor Learning Area
- Replace HVAC Equipment (Including DDC controls for BMS integration)
- Kitchen Upgrades (including fire suppression at hood)
Osborn Middle School
- 3-Way Valves Integrated Into Chiller System
- New Heat Exchanger
- Replace One Chiller System
- Roofing
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Upgrade
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Solano Elementary School
- Replace 60 R22 Rooftop Units
- Replace Roofing at Flat Roof Areas
- Special Education Restroom Renovation
- Solano STRIVE Playground Expansion - COMPLETED
- Solano Restroom Renovation - COMPLETED
- Solano Site Circulation Improvements - COMPLETED
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Upgrade
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
-
2026-2028
Approx. $35 MillionClarendon Elementary School
- Shade Structures (Asphalt area on south side by playground and basketball courts)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Encanto Elementary School
- Paint School
- Shade Structures (South field and cafeteria entrance)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Longview Elementary School
- Expand Kindergarten Playground
- Mechanical Room Lighting
- Heat Strips (To move away from boiler)
- Shade Structures (At gate by ball field)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Montecito Community School
Osborn Middle School
- Band & Music Room Renovation
- Art Room Renovation/Expansion
- Wood Shop Conversion to Maker Space
- Shade Structures
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Solano Elementary School
- Cafeteria Renovation (Eating space and kitchen items)
- Drop-off/Missouri Walking Link
- Drop-off Asphalt Replacement
- Anticipated Enrollment Increase/Campus Growth
- Shade Structures
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
-
2028-2030
Approx. $30 MillionClarendon Elementary School
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Encanto Elementary School
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Longview Elementary School
- Replace Existing Metal Roofing
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Montecito Community School
Osborn Middle School
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Solano Elementary School
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
-
2030-2032
Approx. $5 MillionComing Soon!

-
Phase 1
- New Playground - COMPLETED
- Relocate Volleyball Court to Center Basketball Court
- Roofing
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 2
- Shade Structures (Asphalt area on south side by playground and basketball courts)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 3
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 4 - Coming Soon!
-
Phase 1
- Add Play Structures and Expand Playground
- Roofing
- Weatherization
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 2
- Paint School
- Shade Structures (South field and cafeteria entrance)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 3
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 4 - Coming Soon!
-
Phase 1
- Replace Existing Domestic HW Loop
- Replace Boiler
- Replace Existing Elevator
- Audio/Video for Stage, Lobby, and Gym
- New Marquee
- Phone System Update
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 2
- Expand Kindergarten Playground
- Mechanical Room Lighting
- Heat Strips (To move away from boiler)
- Shade Structures (At gate by ball field)
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 3
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 4 - Coming Soon!
-
Phase 1
- Interior Classroom Reconfigurations and Improvements to Meet District Standards
- Replace Elevator
- Replace Roof
- Parking Lot Renovation
- Screening Along 7th Street
- Develop Outdoor Learning Area
- Replace HVAC Equipment (Including DDC controls for BMS integration)
- Kitchen Upgrades (including fire suppression at hood)
Phase 2 - Coming Soon!
Phase 3 - Coming Soon!
Phase 4 - Coming Soon!
-
Phase 1
- 3-Way Valves Integrated Into Chiller System
- New Heat Exchanger
- Replace One Chiller System
- Roofing
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Upgrade
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 2
- Band & Music Room Renovation
- Art Room Renovation/Expansion
- Wood Shop Conversion to Maker Space
- Shade Structures
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 3
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 4 - Coming Soon!
-
Phase 1
- Replace 60 R22 Rooftop Units
- Replace Roofing at Flat Roof Areas
- Special Education Restroom Renovation
- Solano STRIVE Playground Expansion - COMPLETED
- Solano Restroom Renovation - COMPLETED
- Solano Site Circulation Improvements - COMPLETED
- Audio/Video for Stage and Lobby
- New Marquee
- Phone System Upgrade
- Install Lining in All Sani-Sewer Pipes
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 2
- Cafeteria Renovation (Eating space and kitchen items)
- Drop-off/Missouri Walking Link
- Drop-off Asphalt Replacement
- Anticipated Enrollment Increase/Campus Growth
- Shade Structures
- Flexible Classroom Furnishings
- Outdoor Learning Areas
- General Classroom Reconfigurations
- Security Camera and Intercom Improvements
- Update Kitchen Equipment
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 3
- Examine/Recommission Primary Electrical Equipment
- Lifecycle Projects (Carpet, paint, etc.)
Phase 4 - Coming Soon!
-
Full District Projects
-
Monthly Bond Updates (Governing Board Presentations)
-
Annual Bond Reports